|  | Formulae to auto adjust timings based on percentage |  | |
| | | Patrick |  |
| Posted: Thu Sep 04, 2008 12:40 am Post subject: Formulae to auto adjust timings based on percentage |  |
| |  | |
I have been trying to work this oine out and cant get my mind around it,
Basicaly I have a timing list generated in a spreadsheed, inside that spreadsheet these timings are broken down into percentages of time needed to complete the task, all adding to 100% of the total time given.
Another part of the spreadsheet has times for rest, ie lunch, sleep etc, Im looking for a formula that will take the differance from the time spent on rest and subtract it from the total time on the timeline, then re calculate the timeline based on time left over after the rest has been subracted not incorporateing the rest time.
The start and finishing times must remain the same
Each task takes a certan percentage of the total time allocated for the purpose of this all tasks can be divided evenly.
A1 B1 Conferance A 03 0730 K Sep 08 Meeting 1 03 2212 K Sep 08 Meeting 2 04 0533 K Sep 08 Conferance B 04 1255 K Sep 08 Conferance C 04 2016 K Sep 08 Meeting 3 05 0337 K Sep 08 Final planning Meeting 05 1820 K Sep 08 Tasks Complete By 04 0520 K Sep 08
A11 B11 REST 04 1200 K Sep 08 05 1300 K Sep 08 (lunch) REST 05 2200 K Sep 08 06 0500 K Sep 08 (sleep) REST
If anyone could help with this I would be very gratefull. |
| |
| | | Patrick |  |
| Posted: Thu Sep 04, 2008 1:34 am Post subject: RE: Formulae to auto adjust timings based on percentage |  |
| |  | |
I think I may have explained this poorly, Basicly I am given a task to perform, and we apply a rule called the 1/3 2/3 rule, of the total time given for the task I must use 1/3 of the time to finish my tasks, which allows 2/3 of the time allocated for those further down the chain to complete their tasks.
I have the formulas set to allocate my time and my tasks based on that allocated to me, but I then need it to recalculate rest periods with in my 1/3 of the allocated tasks, Then I can send this out to my staff so that our tasks are finished in the allocated time.
"Patrick" wrote:
| Quote: | I have been trying to work this oine out and cant get my mind around it,
Basicaly I have a timing list generated in a spreadsheed, inside that spreadsheet these timings are broken down into percentages of time needed to complete the task, all adding to 100% of the total time given.
Another part of the spreadsheet has times for rest, ie lunch, sleep etc, Im looking for a formula that will take the differance from the time spent on rest and subtract it from the total time on the timeline, then re calculate the timeline based on time left over after the rest has been subracted not incorporateing the rest time.
The start and finishing times must remain the same
Each task takes a certan percentage of the total time allocated for the purpose of this all tasks can be divided evenly.
A1 B1 Conferance A 03 0730 K Sep 08 Meeting 1 03 2212 K Sep 08 Meeting 2 04 0533 K Sep 08 Conferance B 04 1255 K Sep 08 Conferance C 04 2016 K Sep 08 Meeting 3 05 0337 K Sep 08 Final planning Meeting 05 1820 K Sep 08 Tasks Complete By 04 0520 K Sep 08
A11 B11 REST 04 1200 K Sep 08 05 1300 K Sep 08 (lunch) REST 05 2200 K Sep 08 06 0500 K Sep 08 (sleep) REST
If anyone could help with this I would be very gratefull.
|
|
| |
|
|